Wastewater Capital Projects

VICTORIA POND LIFT STATION AND FORCEMAIN

UPDATE 03/22/2023- Consultant is finalizing the geotechnical scope with their subcontractor.

UPDATE 10/05/2022 - Staff has provided review comments to the consultant on their second submitted drawings.


WASTEWATER TREATMENT PLANT - PHASE 1 IMPROVEMENTS


UPDATE 05/17/2023

      Construction Updates:

          o Headworks Structure:

                  continued installing electrical and control wiring for equipment,

                  pump start-up occurred on April 27,

                  gate/screw compactor start-up on May 2,

                  electrical contractor (TGE) started ground rings;

          o Sitework:

                 TGE continued installing cable tray,

                 installed 24-inch FEB emergency overflow,

                 TGE started electrical work on FEB flowmeter,

                 FEB gate and aeration basin;

          o UV Structure:

                 TGE started running cable to equipment,

                 TGE started ground rings;

          o Influent Flow Meter Vault:

                completed electrical and I&C installation;

          o Effluent Flow Meter Vault:

                continued electrical and I&C installation;

          o Electrical Building:

                continued installation of electrical equipment,

                TGE received 12 of 12 VFDs and installed them,

                Installed sidewalk,

                Switchgear startup,

                VFD startup,

                HVAC startup.

 Other Updates:

Due to a delayed receipt of some electrical equipment (variable frequency drives and programmable logic controllers), the contractor has submitted a time-extension only request (change order) to extend the substantial completion by 154 calendar days making the substantial completion date 11/1/23.  The contractor plans on starting up the new headworks by the end of May.