- Home
- Government
- Departments
- Engineering
- Wastewater Capital Projects
Wastewater Capital Projects
VICTORIA POND LIFT STATION AND FORCEMAIN
UPDATE 03/22/2023- Consultant is finalizing the geotechnical scope with their subcontractor.
UPDATE 10/05/2022 - Staff has provided review comments to the consultant on their second submitted drawings.
WASTEWATER TREATMENT PLANT - PHASE 1 IMPROVEMENTS
UPDATE 05/17/2023
Construction Updates:
o Headworks Structure:
continued installing electrical and control wiring for equipment,
pump start-up occurred on April 27,
gate/screw compactor start-up on May 2,
electrical contractor (TGE) started ground rings;
o Sitework:
TGE continued installing cable tray,
installed 24-inch FEB emergency overflow,
TGE started electrical work on FEB flowmeter,
FEB gate and aeration basin;
o UV Structure:
TGE started running cable to equipment,
TGE started ground rings;
o Influent Flow Meter Vault:
completed electrical and I&C installation;
o Effluent Flow Meter Vault:
continued electrical and I&C installation;
o Electrical Building:
continued installation of electrical equipment,
TGE received 12 of 12 VFDs and installed them,
Installed sidewalk,
Switchgear startup,
VFD startup,
HVAC startup.
Other Updates:
Due to a delayed receipt of some electrical equipment (variable frequency drives and programmable logic controllers), the contractor has submitted a time-extension only request (change order) to extend the substantial completion by 154 calendar days making the substantial completion date 11/1/23. The contractor plans on starting up the new headworks by the end of May.